sitemap
References
Completed in 2013

Tõrva Gymnasium boiler plant

Project manager: Aivar Midri
Site manager: Tarmo Türk
Completed: 2013

Molycorp Silmet storage LMF

Project manager: Kaspar Riis
Site manager: Harry Holtsmann
Completed: December 2013

Balti Jaama Selver (supermarket)

Project manager: Ahti Järvet
Site manager: Silver Kübar
Gross area: 860 m2
Completed: November 2013

Stage III of Arke meat plant

Project manager: Aivar Midri
Site manager: Peep Jõgiste
Gross area: 1010 m2
Completed: October 2013

Fennobed production building

Project manager: Ahti Järvet
Site manager: Tarmo Türk
Gross area: 4913 m2
Completed: January 2014

Silsteve warehouse building

Project manager: Kuldar Ilus
Site manager: Urmas Kalmann
Gross area: 4000 m2
Completed: November 2013

Silsteve warehouse building

Project manager: Kuldar Ilus
Site manager: Urmas Kalmann
Gross area: 4000 m2
Completed: August 2013

Silsteve warehouse building

Project manager: Kuldar Ilus
Site manager: Urmas Kalmann
Gross area: 4000 brm2
Completed: May 2013

Private residence in Rakvere

Project manager: Ahti Järvet

Site manager: Silver Kübar

Gross area: 170 brm2

Completed: March 2013

Ökosil lab building

Project manager: Kaspar Riis
Site manager: Harry Holtsmann
Gross area: 16569 brm2
Completed: April 2013

Arke meat plant slaughterhouse

Project manager: Aivar Midri
Site manager: Peep Jõgiste
Gross area: 1010 brm2
Completed: May 2013

Pühajärve holiday home biofuel-based boiler plant

Project manager: Aivar Midri

Site manager: Tarmo Türk

Gross area: 786 brm2

Completed: April 2013