Molycorp Silmet production building number 53

Project manager: Kaspar Riis
Site manager: Harry Holtsmann
Gross area: 300 m2
Completed: September 2016

Silsteve warehouse buildings, number 1a, 2a and 3a

Project manager: Kuldar Ilus
Site manager: Harry Holtsmann
Gross area: 3×4000 m2
Completed: September 2016

Äri- ja büroohoone Tallinna tn 105, Viljandi

Project manager: Kaspar Riis
Site manager: Taavi Lang
Gross area: 2316 m2
Completed: march 2016

Arcwood tootmis- ja olmehoone Põlvas

Project manager: Peep Jõgiste
Site manager: Silver Kübar
Gross area: 8820 m2
Completed: September 2016

Rimi shop in Põhja pst

Project manager: Ahti Järvet
Site manager: Silver Kübar
Gross area: 1300 m2
Completed: August 2016

Apartment building in Pärnu, Villa 1

Project manager: Aivar Midri
Site manager: Tarmo Türk
Gross area: 2484 m2
Completed: July 2016
www.lvm.ee/villa1

Apartment and Commercial Building in Tallinn, Pärnu street 126

Project manager: Ahti Järvet
Site managers: Silver Kübar, Kaido Kasekamp
Gross area: 7526 m2